Multiple Choice
Which of the following is not true regarding top-down budgeting?
A) It is based on the collective judgments of top and middle managers.
B) Overall project costs are estimated by top and middle managers and then passed on to the next lower level.
C) The overall budget cost is generally not very accurate.
D) Overlooking small but important tasks can lead to a serious budgetary problem.
E) All of the above are true concerning top-down budgeting.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: By very careful planning, a project manager
Q2: Budgeting a project is often more difficult
Q11: Mechanical tasks typically have higher learning rates
Q13: Which of the following statements is not
Q20: A requirement of top-down budgeting is:<br>A) involvement
Q25: Because project budgeting is for a special
Q25: List the steps in performing FMEA.
Q27: Scenario analysis is not a popular technique
Q28: What is the Game Theory approach?
Q69: The first unit requires 10 hours to