Multiple Choice
Which of the following processes of Scope Management Process decomposes or divides the major project deliverables into smaller and more manageable components?
A) Collect Requirements
B) Define Scope
C) Create Work Breakdown Structure
D) Validate Scope
E) Control Scope
Correct Answer:

Verified
Correct Answer:
Verified