Multiple Choice
An estimation technique characterized by the dividing the project into smaller modules and then directly estimating the time and effort in terms of person-hours, person-weeks, or person-months for each module best describes
A) Guesstimating
B) Delphi Technique
C) Time Boxing
D) Top-Down Estimating
E) Bottom-Up Estimating
Correct Answer:

Verified
Correct Answer:
Verified