Multiple Choice
An activity being analyzed under PERT was judged to most likely have a duration of 40 days.When considering the time it would take to complete the activity if every relevant factor went well, it was estimated to be able to be doable in 20 days and even under the worst case imaginable, the task would be take 50 days.The estimates PERT duration of that activity is:
A) 36.67 days
B) 38.33 days
C) 37.50 days
D) 28.33 days
E) 32.67 days
Correct Answer:

Verified
Correct Answer:
Verified
Q36: The tool most closely associated with activity
Q37: What is the difference between crashing and
Q38: The project budget is determined by the
Q39: Once the project schedule and project budget
Q40: _ is well suited for developing simulations
Q42: Installing the operating system on a computer
Q43: How does the work breakdown structure (WBS)
Q44: Why do many people inflate their estimates?
Q45: The critical path has zero slack (or
Q46: The amount of time an activity can