Multiple Choice
_____ is well suited for developing simulations where the project manager can conduct sensitivity analysis for schedule planning and risk analysis.
A) Project Network Diagrams
B) Gantt Charts
C) PERT
D) Activity on the Node
E) Critical Path Analysis
Correct Answer:

Verified
Correct Answer:
Verified