Critical Chain Project Management (CCPM) Is Based on the Idea

Question 7

Multiple Choice

Critical Chain Project Management (CCPM) is based on the idea that


A) people often inflate or add cushioning to their time estimates
B) PERT/CPM was developed in the 1950s so it is too old to be of any use
C) Precedence Diagramming only considers the critical path of a project
D) all of these
E) none of these

Correct Answer:

verifed

Verified