Multiple Choice
Critical Chain Project Management (CCPM) is based on the idea that
A) people often inflate or add cushioning to their time estimates
B) PERT/CPM was developed in the 1950s so it is too old to be of any use
C) Precedence Diagramming only considers the critical path of a project
D) all of these
E) none of these
Correct Answer:

Verified
Correct Answer:
Verified