Three team members are given the task of estimating activity durations.Mr.Optimist estimates the activity to take 2 days to complete.Ms.Pessimist estimates the activity to take 5 days.Mrs.Realist claims that the most likely estimate is 4 days.What should their PERT analysis assign as an expected duration for the activity and what are the benefits and implications of deploying this tool?
Correct Answer:

Answered by ExamLex AI
The PERT analysis should assign an expec...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Answered by ExamLex AI
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q1: The kick-off meeting brings closure to the
Q2: Rolling wave planning is:<br>A) developing a large
Q3: The cost of labor for using a
Q5: Start-to-Start and Finish-to-Finish relationships allow activities to
Q6: Adding resources to an activity to shorten
Q7: Critical Chain Project Management (CCPM) is based
Q8: _ can be useful for tracking and
Q9: Which of the following statements are true?:<br>A)
Q10: What is a kick-off meeting? What purpose
Q11: Describe the Precedence Diagramming Method along with