Multiple Choice
The final step in determining the cost of an activity is:
A) determine necessary resources.
B) determining resource quantity
C) determining the cost of each resource
D) ensuring resources are leveled
E) none of these
Correct Answer:

Verified
Correct Answer:
Verified