menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Technology Project Management Study Set 1
  4. Exam
    Exam 6: The Work Breakdown Structure and Project Estimation
  5. Question
    Funds Allocated for Unexpected Expenses Are _____
Solved

Funds Allocated for Unexpected Expenses Are _____

Question 56

Question 56

Multiple Choice

Funds allocated for unexpected expenses are _____


A) Direct Costs
B) Indirect Costs
C) Sunk Costs
D) Learning Curve Costs
E) Reserves Costs

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q51: Starting the next task before the first

Q52: Completing activities in parallel is called_<br>A) slacking.<br>B)

Q53: Costs incurred prior to the current project

Q54: Describe the steps necessary for estimating the

Q55: Scheduling other projects so that resources may

Q57: Rent, utilities, insurance and administrative costs are

Q58: Define the following and give a real

Q59: Sunk costs include such things as rent,

Q60: The critical path is the shortest path

Q61: The final step in determining the cost

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines