Multiple Choice
Risks may be positive or negative. For a positive risk, a project manager would want to _____.
A) accept the risk
B) share ownership
C) avoid the risk
D) reduce the impact of the risk
E) transfer the risk
Correct Answer:

Verified
Correct Answer:
Verified