Multiple Choice
Through _____, the project manager will scan the project environment to watch for risks as they may arise.
A) risk identification
B) risk assessment
C) risk planning
D) risk monitoring and control
E) risk strategies
Correct Answer:

Verified
Correct Answer:
Verified