menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management in Practice Study Set 1
  4. Exam
    Exam 5: Scheduling the Project
  5. Question
    A Gantt Chart Can NOT Depict a Critical Path,only a PERT/CPM
Solved

A Gantt Chart Can NOT Depict a Critical Path,only a PERT/CPM

Question 21

Question 21

True/False

A Gantt chart can NOT depict a critical path,only a PERT/CPM chart can.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q2: What is the standard deviation of a

Q13: A start-to-finish linkage is the most common

Q55: Which of the following is NOT an

Q56: A project schedule is a project action

Q63: Milestones cannot be identified on a Gantt

Q66: An identifiable state resulting from the completion

Q75: Technical dependencies are often harder to see

Q88: The amount of time a noncritical task

Q95: An event is a series of connected

Q106: Critical path tasks always have zero slack.

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines