Multiple Choice
The first step in the creation of a PERT/CPM chart is to ____.
A) determine the logical order of project tasks
B) identify the graphical planning aids to use
C) identify all the project tasks
D) determine the status of all tasks
Correct Answer:

Verified
Correct Answer:
Verified