Multiple Choice
Microsoft's risk management model includes ____.
A) category, which specifies the risk type
B) probability, which indicates the degree of adverse effect should the risk occur, on a scale of 1 to 10
C) impact plan, which identifies plans to control or limit the risk
D) contingency, which identifies a condition that would initiate the contingency plan
Correct Answer:

Verified
Correct Answer:
Verified