    -When Estimating the Duration of a Task, the Project Manager
Solved

-When Estimating the Duration of a Task, the Project Manager

Question 60

Question 60

Short Answer

  -When estimating the duration of a task, the project manager makes three time estimates for the task and then assigns a(n) ____________________, which is an importance value, to each estimate.
-When estimating the duration of a task, the project manager makes three time estimates for the task and then assigns a(n) ____________________, which is an importance value, to each estimate.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q34: System developers can initiate a formal project

Q55: Project management is dynamic and challenging, regardless

Q56: _ is a full-featured program that holds

Q57: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5608/.jpg" alt=" -A(n) _ is

Q58: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5608/.jpg" alt=" -A project is

Q59: In any project, large or small, tasks

Q61: When maintaining schedules, if enough _ and

Q62: A(n) _ chart can be used to

Q64: MATCHING<br>Identify the letter of the choice that

Q65: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5608/.jpg" alt=" -To simplify a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines