Multiple Choice
MATCHING
Identify the letter of the choice that best matches the phrase or definition.
a.project management
f.weight
b.project coordinator
g.bottom-up technique
c.project leader
h.dependent
d.milestone
i.concurrent
e.constraint
j.predecessor
-Which of the following is NOT a true statement about Gantt charts?
A) It is a horizontal bar chart that represents a series of tasks.
B) The position of a bar shows the planned start and end of the task, and the length of the bar indicates its duration.
C) They can show task status in several ways, including the use of a vertical line to represent the current date.
D) They provide the detailed information that is necessary when managing a complex project.
Correct Answer:

Verified
Correct Answer:
Verified
Q34: System developers can initiate a formal project
Q59: In any project, large or small, tasks
Q60: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5608/.jpg" alt=" -When estimating the
Q61: When maintaining schedules, if enough _ and
Q62: A(n) _ chart can be used to
Q65: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5608/.jpg" alt=" -To simplify a
Q66: MATCHING<br>Identify the letter of the choice that
Q67: A project triangle shows three legs: _.<br>A)project
Q68: MATCHING<br>Identify the letter of the choice that
Q69: Gantt charts are an ideal tool for