If a drilling rig operates 10 hours a day and takes 40 hours to drill 8 meters of earth's surface, the productivity of the drilling rig will be _____.


A) 2 meters per day
B) 1 meter per day
C) 0.8 meters per day
D) 0.4 meters per day