Project Task E Has the Following Estimates: (1)optimistic Time -

Question 24

Short Answer

Project task E has the following estimates: (1)optimistic time - 10 days, (2)Pessimistic time - 20 days, and (3)Most likely time - 12 Days. The standard deviation for time using the beta statistical distribution is ________ days.

Correct Answer: