Multiple Choice
A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a __________.
A) start to finish dependency
B) finish to start dependency
C) finish to finish dependency
D) start to start dependency
Correct Answer:

Verified
Correct Answer:
Verified