Multiple Choice
__________ is one of the four dimensions of project success,and is focused on meeting both the budget and schedule established in the project plan.
A) Project efficiency
B) Customer impact / satisfaction
C) Business / direct success
D) Future potential
Correct Answer:

Verified
Correct Answer:
Verified