Question 54

Question 54

Multiple Choice

__________ is a measure of the degree to which the output of a system conforms to pre-specified characteristics.


A) Scope
B) Quality
C) Cost
D) Schedule

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q49: Discuss some of the problems associated with

Q50: There are tough problems associated with finding

Q51: During the audit,the auditor / evaluator must

Q52: We have seen a rise in agile

Q53: The stated project objectives,including funder satisfaction,are part

Q55: A meeting place for the project team,a

Q56: _ tries to capture the essence of

Q57: The _ dimension of project success includes

Q58: The formal audit report may be presented

Q59: Identification of the ancillary goals of a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines