Multiple Choice
To define the ____ of the project accurately,it is very important to ensure consistency between the project charter,scope statement,WBS,Gantt chart,and related documents.
A) scope
B) charter
C) vision
D) parameters
Correct Answer:

Verified
Correct Answer:
Verified