Multiple Choice
A three-point estimate is an estimate that includes a(n) ____,most likely,and pessimistic estimate,such as three weeks,four weeks,and five weeks,respectively.
A) optimistic
B) unusual
C) remote
D) conditional
Correct Answer:

Verified
Correct Answer:
Verified