Multiple Choice
____ includes the actual amount of time spent working on an activity plus elapsed time.
A) Extension
B) Duration
C) Period
D) Length
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q17: The term "_" is used to describe
Q18: You need a detailed project schedule before
Q19: A cost baseline is a(n)_ budget that
Q20: The main purpose of project planning is
Q21: Project _ management includes the processes required
Q23: A work _ is a task at
Q24: Activity sequencing involves reviewing the activity list
Q25: As more information becomes available and decisions
Q26: The project team should review an activity
Q27: What is the PERT weighted average based