    What Is the PERT Weighted Average Based on an Optimistic
Solved

What Is the PERT Weighted Average Based on an Optimistic

Question 27

Question 27

Multiple Choice

What is the PERT weighted average based on an optimistic estimate of six days,a most likely estimate of eight days,and a pessimistic time of twelve days?


A) six
B) eight
C) eleven
D) twelve

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q22: _ includes the actual amount of time

Q23: A work _ is a task at

Q24: Activity sequencing involves reviewing the activity list

Q25: As more information becomes available and decisions

Q26: The project team should review an activity

Q28: People are more likely to perform well

Q29: In an AOA network diagram,a(n)_ occurs when

Q30: The main output of scope definition is

Q31: There is usually no cost or duration

Q32: The format of the WBS dictionary can

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines