Multiple Choice
Champion Cooling has just signed a contract to assemble window air conditioners for another company.The list of tasks,including time requirements and immediate predecessors,follows.Initially,the plan was to make 300 units in an eight hour day but as the summer months approach,Champion Cooling finds themselves far behind in total production.They wish to reconfigure their production line in order to produce maximum output.What should their takt time be?
A) 5
B) 6
C) 7
D) 10
Correct Answer:

Verified
Correct Answer:
Verified