The process design team at a manufacturer has broken an assembly process into eight basic steps,each with a required time,and predecessor as shown in the table.There are 8 productive hours available in a day and the manufacturer wishes to produce 400 units.
The process design team at a manufacturer has broken an assembly process into eight basic steps,each with a required time,and predecessor as shown in the table.There are 8 productive hours available in a day and the manufacturer wishes to produce 400 units.    -What is the theoretical minimum number of stations? A) four B) five C) six D) seven
-What is the theoretical minimum number of stations?


A) four
B) five
C) six
D) seven