The process design team at a manufacturer has broken an assembly process into eight basic steps,each with a required time,and predecessor as shown in the table.There are 8 productive hours available in a day and the manufacturer wishes to produce 400 units.
-What is the theoretical minimum number of stations?
A) four
B) five
C) six
D) seven
Correct Answer: