Multiple Choice
This Gantt chart can be used to show:
A) activity D must come before activity C.
B) activity F can be done at the same time as D.
C) activity E can begin as soon as activity A is complete.
D) activities D and B can be done simultaneously.
Correct Answer:

Verified
Correct Answer:
Verified