Multiple Choice
What is the fastest completion time of the project with activity lengths (in days) and precedence requirements as shown in the table?
A) 22
B) 25
C) 27
D) 30
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q3: What is the total cost to complete
Q7: There are more resources required during the
Q14: The budget estimates made during the concept
Q17: A hatmaker,fresh off a very successful showing
Q21: This Gantt chart can be used to
Q22: What are the early and late start
Q23: PERT is an acronym meaning:<br>A)Project Evaluation and
Q24: For critical path activities,slack is _.
Q38: The Guide to the Project Management Body
Q53: _ is a technique to shorten the