    What Is the Latest That Activity D Can Start If
Solved

What Is the Latest That Activity D Can Start If

Question 5

Question 5

Multiple Choice

What is the latest that activity D can start if A is 5 days,B is 7 days,C is 4 days,D is 5 days,E is 7 days,and F is 6 days long? What is the latest that activity D can start if A is 5 days,B is 7 days,C is 4 days,D is 5 days,E is 7 days,and F is 6 days long?   A) 14 B) 15 C) 16 D) 17


A) 14
B) 15
C) 16
D) 17

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: A project is composed of the twelve

Q1: Project planners develop a broad definition of

Q2: A forward pass through a network is

Q4: A performance or time target for each

Q7: The project shown below has crash costs

Q8: A project is comprised of 6 activities

Q9: What is the latest that activity B

Q15: Most project management software represents a project

Q40: Discuss the recent business trends that have

Q50: Performance or time targets for each major

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines