    What Is the Latest That Activity B Can Start If
Solved

What Is the Latest That Activity B Can Start If

Question 9

Question 9

Multiple Choice

What is the latest that activity B can start if A is 35 days,B is 5 days,C is 6 days,and D is 7 days long? What is the latest that activity B can start if A is 35 days,B is 5 days,C is 6 days,and D is 7 days long?   A) 35 B) 36 C) 40 D) 41


A) 35
B) 36
C) 40
D) 41

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Project planners develop a broad definition of

Q5: What is the latest that activity D

Q7: The project shown below has crash costs

Q8: A project is comprised of 6 activities

Q13: A hatmaker,fresh off a very successful showing

Q15: Most project management software represents a project

Q35: An expectation that a new building's foundation

Q40: Discuss the recent business trends that have

Q50: Performance or time targets for each major

Q53: _ is a technique to shorten the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines