Multiple Choice
What is the latest that activity B can start if A is 35 days,B is 5 days,C is 6 days,and D is 7 days long?
A) 35
B) 36
C) 40
D) 41
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: Project planners develop a broad definition of
Q5: What is the latest that activity D
Q7: The project shown below has crash costs
Q8: A project is comprised of 6 activities
Q13: A hatmaker,fresh off a very successful showing
Q15: Most project management software represents a project
Q35: An expectation that a new building's foundation
Q40: Discuss the recent business trends that have
Q50: Performance or time targets for each major
Q53: _ is a technique to shorten the