Multiple Choice
A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below.
-Which of these statements is BEST?
A) Only four of these activities have zero slack.
B) The late finish of D minus the late finish of C is less than the slack of B.
C) B's late start plus its slack equals F's late finish.
D) The sum of the late start values for activities A through E is less than the sum of the late start values for F and G.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Project planners develop a broad definition of
Q8: A project is comprised of 6 activities
Q9: What is the latest that activity B
Q14: The budget estimates made during the concept
Q15: Most project management software represents a project
Q17: A hatmaker,fresh off a very successful showing
Q23: PERT is an acronym meaning:<br>A)Project Evaluation and
Q35: An expectation that a new building's foundation
Q38: The Guide to the Project Management Body
Q53: _ is a technique to shorten the