_____ Developed Resource Plans Based on Forecasts of Orders in Generic

Question 87

Multiple Choice

_____ developed resource plans based on forecasts of orders in generic units such as standard hours.


A) The master production schedule (MPS)
B) Linear programming
C) Aggregate scheduling
D) Material requirements planning (MRP)