Multiple Choice
The overriding objective of line-balancing is
A) to split operations between different stations so as to minimize the number of stations.
B) to achieve a balance of production resources that can deliver the right amount of production to satisfy demand requirements with minimum waste of resources.
C) to be clever about process design so as to achieve cycle time reduction with minimum defectives.
D) none of the above
Correct Answer:

Verified
Correct Answer: