Multiple Choice
In _____,project activities are the connecting arrows.Each arrow starts with a numbered node and ends with a larger numbered node.The arrow can be identified by these numbers.
A) AOL
B) AON
C) AOA
D) EOA
Correct Answer:

Verified
Correct Answer:
Verified