Multiple Choice
Every event node in the PERT network is identified with a four-part scorecard. Which of the following is the correct four-part scorecard?
A) EF ES LS LF
B) ES EF LS LF
C) ES EF LF LS
D) ES LF LS EF
Correct Answer:

Verified
Correct Answer:
Verified