Essay
H & W construction have been awarded a job to replace the vinyl and carpet throughout Mr.Bruce's house.The team has prepared the following estimates.Below are the activities and times for installing a laminate floor.
Construct the appropriate network diagram and label the ES,EF,LS,and LF times.Alternatively,create the table of ES,EF,LS,and LF.What is the critical path? How many hours are in the critical path? Mrs.Bruce needs this time estimate to plan an upcoming party.Mrs.Bruce is hosting a house and garden party for her daughter,Daisy,and is anxious for the team to complete the project.H & W Construction will be paid an extra $15 per hour for early completion (any time less than the critical path).Tasks B,I,and J can be shortened.B by 2 hours;I and J by 5 hours;each reduction will cost $12 per hour.Which if any of the three tasks will you shorten?
Correct Answer:

Verified
The critical path = A,C,E,F,H,I,J,L
Th...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
The critical path = A,C,E,F,H,I,J,L
Th...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q31: If specific technical,technological,and production skill information can
Q32: When the variance of a noncritical project
Q33: Good project-management methods do which of the
Q34: Slack (associated with an activity) describes the
Q35: A Gantt project-planning chart is good for
Q37: _enables the critical path to be identified
Q38: _ is when each activity will be
Q39: When activities are represented as arrows,then the
Q40: Normal time is associated with the minimum
Q41: Every event node in the PERT network