Multiple Choice
For cost estimates,when project bidding is used,underestimating the cost of a job results in _____.
A) bids that are too low
B) probability of losing money
C) higher probabilities of the bid being accepted
D) both a and b
E) all of the above
Correct Answer:

Verified
Correct Answer:
Verified