Multiple Choice
Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?
A) Defining activities
B) Sequencing activities
C) Developing the schedule
D) Estimating activity durations
Correct Answer: