The Critical Path Is the _____ Path Through a Network

Question 37

Multiple Choice

 The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.


A) longest; longest
B) longest; shortest
C) shortest; longest
D) shortest; shortest

Correct Answer: