Multiple Choice
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
A) longest; longest
B) longest; shortest
C) shortest; longest
D) shortest; shortest
Correct Answer:

Verified
Correct Answer:
Verified