Which of the Following Documents Is Most Likely to Include

Question 38

Multiple Choice

Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?


A) Resource breakdown structure
B) Milestones list  
C) Organizational process assets update
D) Project charter

Correct Answer: