Multiple Choice
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
A) critical paths
B) feeding buffers
C) dummy activities
D) fast tracking
Correct Answer:

Verified
Correct Answer:
Verified