    If a Liquidated Damages Clause Demands an Unusually Large Sum
Solved

If a Liquidated Damages Clause Demands an Unusually Large Sum

Question 1

Question 1

Multiple Choice

If a liquidated damages clause demands an unusually large sum that is not related to reasonably-anticipated actual damages,the clause will be held to be void as a(n) :


A) penalty.
B) unliquidated damages clause.
C) Extortion
D) Blackmail

Correct Answer:

verifed

Verified

Related Questions

Q3: When one party has broken a contract,there

Q10: An anticipatory repudiation must be clear,absolute,and unequivocal.

Q13: The "American rule" states that the losing

Q14: When one party commits a non-material breach

Q21: If monetary damages would be an adequate

Q25: Ordinarily, contracts for the performance of personal

Q37: If a seller delivers defective goods, the

Q41: The remedy of specific performance will most

Q46: When a party expressly declares before the

Q57: If a plaintiff seeking damages in a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines