Multiple Choice
Which of the following is used to organize and summarize ideas or issues generated by team members?
A) burndown chart
B) affinity diagram
C) check sheet
D) Kano model
Correct Answer:

Verified
Correct Answer:
Verified
Q51: Affinity diagram procedures include brainstorming an exhaustive
Q52: PDCA stands for<br>A)perform,document,control,analyze.<br>B)plan,do,check,act.<br>C)plan,design,control,accept.<br>D)perform,develop,convert,activate.
Q53: QFD does each of the following <b>except</b><br>A)acts
Q54: Which TMAP step improvises the team thought
Q55: Which of the following Kano Model requirements
Q57: Brainstorming works well if team members build
Q58: When compared to the other Kano model
Q59: Pareto charts are usually used when analyzing
Q60: Advantages of using a burndown chart include<br>A)stakeholders
Q61: Check sheets graphically illustrate the causes of