Multiple Choice
The maximum price the client expects to pay a contractor regardless of cost overruns in a project best defines
A) target price.
B) celling price.
C) maximum price.
D) nonnegotiable price.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q44: The structure of the WBS should consider
Q45: Documents prepared during the project planning stages
Q46: The overall objective of the scope management
Q47: A requirement is a condition needed by
Q48: The process improvement plan defines the acceptable
Q50: The purpose of the process improvement plan
Q51: Small project activities possibly with very short
Q52: Which of the following types of contracts
Q53: Stages in the procurement cycle include each
Q54: What is a quality management plan? What