Multiple Choice
Which of the following types of contracts pays the contractor allowable performance costs along with a predetermined percentage based on actual total costs?
A) cost-plus incentive fee contract
B) guaranteed maximum-shared savings contract
C) cost-plus fixed fee contract
D) cost-plus percentage fee contract
Correct Answer:

Verified
Correct Answer:
Verified
Q47: A requirement is a condition needed by
Q48: The process improvement plan defines the acceptable
Q49: The maximum price the client expects to
Q50: The purpose of the process improvement plan
Q51: Small project activities possibly with very short
Q53: Stages in the procurement cycle include each
Q54: What is a quality management plan? What
Q55: Which of the following establishes the requirements,requirement
Q56: What is a contract? List six types
Q57: When creating a WBS,you should keep in