Causing a delay to a subsequent activity is called


A) free float.
B) designated slack.
C) reduced slack.
D) total float.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q43: An activity on the critical path has

Q44: Shortening an activity is called<br>A)float.<br>B)crash.<br>C)reduction.<br>D)smoothing.

Q45: The ratio of rise and run of

Q46: A specific task,or set of tasks,that is

Q47: Multitasking is when a resource is responsible

Q49: Advantages of PERT include<br>A)inexpensive to maintain.<br>B)flexibility.<br>C)easy to

Q50: Which of the following was developed by

Q51: In CCPM,a finite amount of time that

Q52: Free float is an early warning and

Q53: The shortest time an activity can be

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines