    Which of the Following Was Developed by Du Pont De
Solved

Which of the Following Was Developed by Du Pont De

Question 50

Question 50

Multiple Choice

Which of the following was developed by Du Pont de Nemours & Co.and Remington Rand Corporation?


A) PERT
B) CPM
C) TMAP
D) QFD

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q45: The ratio of rise and run of

Q46: A specific task,or set of tasks,that is

Q47: Multitasking is when a resource is responsible

Q48: Causing a delay to a subsequent activity

Q49: Advantages of PERT include<br>A)inexpensive to maintain.<br>B)flexibility.<br>C)easy to

Q51: In CCPM,a finite amount of time that

Q52: Free float is an early warning and

Q53: The shortest time an activity can be

Q54: A technique to shorten the duration of

Q55: Which of the following demands extensive hardware,is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines