Multiple Choice
For an activity,assume the early start is 3 weeks,early finish is 6 weeks,late start is 4 weeks,and late finish is 7 weeks.What is the activity's slack?
A) 3 weeks
B) 4 weeks
C) 1 week
D) 2 weeks
Correct Answer:

Verified
Correct Answer:
Verified