menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Process Technology
  4. Exam
    Exam 8: Project Scheduling
  5. Question
    For an Activity,assume the Early Start Is 3 Weeks,early Finish
Solved

For an Activity,assume the Early Start Is 3 Weeks,early Finish

Question 66

Question 66

Multiple Choice

For an activity,assume the early start is 3 weeks,early finish is 6 weeks,late start is 4 weeks,and late finish is 7 weeks.What is the activity's slack?


A) 3 weeks
B) 4 weeks
C) 1 week
D) 2 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q61: Dependencies defined by the project team are<br>A)discretionary

Q62: The longest time that an activity might

Q63: Identify and describe three dependencies of project

Q64: Each activity can be crashed at least

Q65: Which of the following includes activities performed

Q67: The amount of time that an activity

Q68: In order to keep the whole project

Q69: An overall management philosophy introduced by Goldratt

Q70: Capacity measures how early or late an

Q71: Basic reasons for creating dependencies of project

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines