    The Longest Time That an Activity Might Require Best Defines
Solved

The Longest Time That an Activity Might Require Best Defines

Question 62

Question 62

Multiple Choice

The longest time that an activity might require best defines


A) expected time.
B) optimistic time.
C) most likely time.
D) pessimistic time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q57: The earliest finish time is the total

Q58: PDM uses time as a common factor

Q59: When working with project management software,factors that

Q60: The shortest time in which an activity

Q61: Dependencies defined by the project team are<br>A)discretionary

Q63: Identify and describe three dependencies of project

Q64: Each activity can be crashed at least

Q65: Which of the following includes activities performed

Q66: For an activity,assume the early start is

Q67: The amount of time that an activity

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines